Substation Expansion
< Back to Projects Dallas, TX
Substation
Substation
The expansion including adding a 50 MVA -C- Transformer to an operation A-B site. This involved working with the utility provider for new service loop connections. Charter set up commissioning and testing for the entire substation.
The capacity for new growth was time sensitive. At that time, lead times for transformers were at 48 weeks for that size custom transformer. There was also rapid growth of the campus data centers, including the need for the 3rd C circuit.
Project Management Services